Multipurpose synchrotron radiation construction project management division promotes industrial use and basic capabilities of science and technology Build the world's best multipurpose radiation accelerator for enhancement.

ISSUE

Basic Plan for the Construction Project of the Multipurpose Synchrotron Radiation Accelerator
  • Writer이**
  • Created2024-12-13
  • Views85

(Total Project Cost) KRW 1.1643 trillion ( Central Govt. Expenditure : KRW 964.3 billion / Local Govt. Expenditure : KRW 200 billion)

(Project Duration) July 2021 December 2029

(Site Area) 540,000(including the basic site area of 310,000)

(Facility Size) 69,959

(Project Proponent/Research Institutions) Ministry of Science and ICT / Chungchungbuk-doCheongju City / KBSI (Leading)POSTECH (Collaborating)

(Project Status)

  ㅇ Accelerator and Beam Line (PAL): Technical Design Report (TDR) published (December 2023), TDR review completed (April 2024), Design Adequacy review completed (July 2024), Total project cost adjustment completed (October 2024).

  ㅇ (Infrastructure (KBSI)) : Working drawings and total project cost adjustment completed (October 2024).

  ㅇ (Site Preparation) 100% progress achieved in the basic site preparation (as of November 2024).